The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week:
Need Help Writing an Essay?
Our team of talented writers is ready to assist. We offer essay writing help in over 75 disciplines, ensuring a convenient and comprehensive solution for all your academic needs!
Get Help Now!Activity | Duration (weeks) | Precedes | Crash Cost/Week |
A (start) | 33 | B, C | $ 380$380 |
B | 22 | E | $ 120$120 |
C | 66 | F | $ 220$220 |
E | 22 | F | $ 160$160 |
F (end) | 22 | long dash— | $ 400$400 |
Suppose that Rafay is only given
88
weeks (instead of
1111)
to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.
Activity | Each Activity Should be Reduced BY
(weeks) |
A | nothing
week(s) Can you help me answer the activities A-F on what each activity should be reduced by (weeks) |
Get Quick Assignment Writing Help – No Plagiarism Guarantee!
Online assignment writing service website that provide university students with original and quality academic essays, term papers, admission essays, annotated bibliographies, reports, scholarship essays, personal statements, research proposals, research papers, projects, presentations, dissertation, theses, movie reviews, Book reviews, application papers, among others.